CURRENT STATUS: Council unanimously supported a motion on 20th August 2026 to investigate practical early-win management options for Bird Lake, including solar aeration & to work with the community on a potential native planting day.
OVERVIEW
About Bird Lake
Bird Lake (Baywood Chase Lake) is an artificial lake in Suffolk Park that forms part of the local stormwater system & flows to Tallow Creek.
The lake has been the subject of investigations into water quality, ecology & potential management options for many years.
WATER QUALITY
Water quality has been identified as a significant concern, including nutrient build-up, algae, low oxygen, sediment accumulation & other pollutants.
THE CATCHMENT
Stormwater from surrounding urban areas enters the lake before flowing towards Tallow Creek, connecting Bird Lake to a much wider catchment.
WILDLIFE & HABITAT
Bird Lake supports birds & other wildlife & forms part of a broader ecological system connected to Tallow Creek & downstream coastal environments.
COMMUNITY ROLE
SPCA is bringing together community knowledge, available evidence & potential solutions to advocate for practical action & a healthier future for Bird Lake.
Our aim is to build a clear picture of the lake, understand the evidence & support practical, achievable action.
DOCUMENTS
The Evidence
Bird Lake has been studied, investigated & discussed for many years.
We've brought the key reports, plans & community evidence together so it's easier to understand what has been found, recommended & considered.
RESEARCH & WATER QUALITY
Technical investigations, water-quality studies & reports examining the condition of Bird Lake, its water quality, pollution sources & the surrounding catchment.
PLANNING & MANAGEMENT
Management plans, Council documents & strategic planning relating to Bird Lake, Tallow Creek & the wider coastal management context.
COMMUNITY & MEDIA
Community consultation, local perspectives & media coverage documenting community concerns, advocacy & the continuing conversation about Bird Lake.
RESTORATION & IMPLEMENTATION
Technical guidance & research relating to potential restoration, stormwater treatment, biofiltration & practical approaches to improving water quality.
We've prioritised the key documents here, with the wider document library available for anyone who wants to explore the evidence further.
SOLUTIONS
Finding a Way Forward
Improving Bird Lake will require practical, evidence-based action alongside longer-term planning for the lake & its catchment.
SPCA is currently exploring potential approaches, with a particular focus on water quality, aeration, monitoring & habitat restoration.
SOLAR AERATION
Council has supported investigation & scoping of a potential solar aeration pilot as one practical early-win option for improving lake conditions
COMMUNITY PLANTING
Council has supported discussions about a potential community planting day to improve vegetation around tributaries & build community understanding of waterway health.
MONITORING
Better monitoring can establish a baseline, measure changes in water quality & help determine whether future interventions are producing meaningful environmental improvements.
COUNCIL ACTION
Council has unanimously supported investigating practical early-win options, including aeration, while longer-term Coastal Management Program work continues.
These approaches are at different stages of development. We'll continue updating this page as evidence, partnerships & opportunities develop.
BIRD LAKE HISTORY
1990 - Lake is constructed
1990 - Bird Lake is constructed
Baywood Chase Lake is constructed as part of the surrounding urban development. It is designed primarily as a stormwater retention basin, receiving runoff from a catchment of approximately 44 hectares. The lake is about 3 hectares in area & includes a sedimentation basin & three small islands.
2012 - Water-quality monitoring
2012 - Water-quality monitoring continues
By this time, Byron Shire Council is periodically monitoring cyanobacteria at the lake. Records reviewed in the 2018 Management Plan show that many samples were above the relevant alert levels, highlighting that poor water quality was an established issue well before the current restoration discussion.
2018 - Lake Management Plan
2018 - First detailed Lake Management Plan
Byron Shire Council commissions Australian Wetlands Consulting to prepare a management plan for Baywood Chase Lake.
The study identifies a range of issues, including poor water quality, algal blooms, low dissolved oxygen, poor-quality stormwater inflows, insufficient aquatic vegetation & impacts associated with the large bird population.
The plan assesses a range of rehabilitation options, including solar aeration, rehabilitation of the sediment basin, native planting, vegetated swales, wetlands & changes to water flows.
2018 - Rehabilitation options identified
2018 - A number of rehabilitation options are identified
The 2018 assessment finds that several options have potential to improve lake health.
Its multi-criteria assessment gives high scores to increasing flows using recycled water, rehabilitating the sediment basin, solar-powered aeration, native planting & vegetated swales.
The plan recommends further assessment of recycled water, restoration of the sediment basin, continued community involvement & specific consideration of bird management.
These were recommendations from a management study, not a program of works that was subsequently implemented.
2023 - Water quality investigations
2023 - Water-quality sources are investigated
A major Byron Shire Council Coastal Management Program study examines pollution sources & potential management options across the Tallow Creek catchment.
For Baywood Chase Lake, the study identifies blue-green algae, pathogens & bacteria, nutrients & low dissolved oxygen as key water-quality concerns. It carries forward several options from the earlier lake plan for further consideration, including solar aeration, sediment-basin rehabilitation, weed removal & native planting, vegetated swales & other stormwater-treatment measures.
2024 - Technical & strategic works
2024 - Further technical & strategic work
Council continues work on the lake through its Coastal Management Program.
The Salients review considers the wider Tallow Creek system, including water quality, flooding, historical management & stakeholder input, recognising that Baywood Chase Lake forms part of the broader catchment rather than being an isolated waterbody.
May 2024 - Community consultation
May 2024 - Council community consultation
Council undertakes community consultation to inform the draft Baywood Chase Lake Management Plan, receiving 146 responses.
The key concerns identified were odour; water quality & algal blooms, birds on the islands, lack of vegetation / bird habitat & general amenity.
September 2024 - Community science
September 2024 - Community science begins to grow
The Echo reports on efforts to clean up Baywood Chase Lake & the wider Tallow Creek catchment.
A community information session is planned, with a citizen-science project proposed to investigate water quality upstream of Tallow Creek. The project would train local participants to identify problems & use digital meters to assess water quality.
This marked an important shift towards community participation & evidence gathering, alongside Council's technical work.
March 2025 - Moved into the CMP
March 2025 - Lake options move into the Coastal Management Program
Council reports that it has reviewed & shortlisted management options for Baywood Chase Lake & is proceeding with their analysis through the Stage 3 Coastal Management Program for the Tallow Creek catchment.
The intention is to assess the options in the broader estuary context, with further community engagement anticipated.
June 2026 - SPCA Survey
June 2026 - Suffolk Park community consultation
Suffolk Park Community Association undertakes its own community consultation, receiving 50 responses.
Every respondent expressed concern about the condition of the lake. 96% supported Council seeking funding to improve it, 88% supported upgrades delivering both stormwater & ecological benefits, 76% supported major upgrades rather than basic maintenance.
The consultation identifies Bird Lake as part of the wider Tallow Creek catchment & Southern Gateway Corridor, reinforcing the case for looking beyond the lake itself.
20 August 2026 - Council motion passed
20 August 2026 - Council unanimously supports early action
Council considers a motion seeking practical action on Baywood Chase Lake while the longer-term Coastal Management Program progresses.
The motion calls for investigation of early-win interventions, including consideration of a solar aeration pilot & discussion with the community & relevant environmental groups about a potential native planting day.
Council votes unanimously in favour.
This does not mean a restoration project has been funded or constructed. It means there is now a Council-supported pathway to investigate practical early interventions while longer-term planning continues.
Current - What happens now?
NOW - Building the restoration pathway
The next stage is about turning the evidence into practical, properly assessed projects; including potential aeration, stormwater treatment, habitat / vegetation improvements, monitoring & longer-term restoration.
SPCA's role is to help keep the community informed, support evidence-based participation & build partnerships around the lake's future. This is intended to complement, rather than replace, Council's Coastal Management Program.